Wednesday, August 30, 2006

August 29

Everyone sure was busy today. People were working everywhere.. Plumbers, electricians, roofers, contractors and the landscapers...

Donna and I were also interviewed today for Turner Publishers..







Monday, August 28, 2006

August 28

We have Windows!! They should have finished putting in the windows this afternoon. They started installing the insulation yesterday. The lobby floor and classroom should be stained by the weekend and some of the landscaping will be done this week. I have also been told that they should start siding the building by the end of the week...







Monday, August 21, 2006

August 21

The main roof is now complete. As I was taking the pictures the roofing crew was busy trimming the edges. Once the sheathing over the entry/classroom and garage are done tomorrow or the next day the roofers will finish the rest of the roof. Windows were delivered and should be in soon. The plumber has been busying installing the drain vents. Every drain has its own vent and we have quite a few of them!





Sunday, August 13, 2006

August 13

Dropped by the site today to see how things were going. As you can see from the photos the roofers are moving along. The building should be weather proof soon...





Wednesday, August 09, 2006

August 9

Hi there, well there was good activity today. The roofers were on site and should have the roof done in about 9 days... Thank goodness we are having nice weather, not sure I would want to be up there when the temperature is in the 90's!

They started construction on one of the dormers. This one will be a vent for exhaust from the HVACs. The other one will be directly over the cat adoption.

The sun tubes have been cut out, we will have 5 of them. Two in the stray dog holding area and 3 in dog adoption.

We have a sub-contractor meeting tomorrow, so I'm hoping for some good news for a completion date... Keep your fingers crossed..